Award of initial 3.5 Year Open Cast Mining Contract on the worlds largest Graphite mine
Contract Value: US$34,689,928.72
Value of Work Completed: US$ 10,637,038.25
Start Date: 3 August 2016
(All figures exclude 17% IVA)
Contract Value: US$ 18,000,000
Value of Work Completed: US$0.00
Value of Preliminary works/ Plant Hire to date: US$60,000.00
Start Date: T.B.A
Construction of Earth Dams for small growers
Commencement Date: August 2017
Contract Value: $180,000.00
Commencement Date: September 2017
Duration: tba
Contract Value: tba
Construction of Tailing Storage Facility Earth Dam
Commencement Date: July 2017
Duration: 4.5 months
Contract Value: US$2.6million
Bulk Sample Extraction Phase # 1 of Graphite reserve on remote site in the Calbo Delgado Province
Commencement Date: May 2017
Current Contract Value: US$+/- $250,000
Contract for Major In pit Haulage operations on Jindal Tete Coal Open Pit.
Contract Value: US$ 7,074,900
Value of Work Completed: US$ 859,605.39
Start Date: 9 February 2019
(All figures exclude 17% IVA)
Duration: 10 Months
Contract Value: $3.8 Million USD
Bush Clearing
2 number Balancing Dams
8.71km Water Pipe Line - 550 ND Classes 6 & 9
Construction of Weir
Commencement Date: October 2017
Duration: 4 months
Contract Value: $890,000
Tayanna were awarded a 15km pipeline linking raw water dam to the processing plant.
Commencement Date: June 2017
Duration: 5 months
Contract Value: US$1.93 million
Principle Mining Contractor on the Montepuez Ruby Green Fields Project
Commencement Date: August 2016
Contract Value to Date: US $1.4 million
Tayanna were the principle mining contractor on the Manica Green Fields Project for Phase 1 of 4 of the Alluvial Gold Mining project.
Commencement Date: August 2016
Duration: 10 year project for the life of the mine
Contract Value: US $2.7 million