Contract Date: April 2016 - November 2016
Contract Value: US$ 700,000
Location: Manica Province, Mozambique
Client: Omnia Mine
Contract Date – April 2016 - July 2016
Contract Value – US$ 450,000
Location - Tete, Mozambique
Development and construction of two shopping malls based in Tete
Contract Date: May 2015 - November 2015
Contract Value: US$ 1.4million
Location: Tete, Mozambique
Client: McCormick Property Developments for Largest Shopping Mall in Tete
Contract Date – July 2014 - November 2014
Contract Value – US$ 4.2 million
Location - Tete
Client - Mota-Engil Mozambique
Contracted to carry out Roadwork’s of 14km’s linking the new bridge spanning the Zambeze River
Completion Date – April 2015
Contract Value – US$ 7,9million
Location - Mozambique
Client - Rio Tinto
Contracted to assist EQSTRA with Topsoil, Subsoil and Bulk Waste stripping.
Total Volume Mined – 3.8 Million BCM’s in 26 Months
Completion Date – 2012 - 2014
Contract Value – US$ 5.8million
Location - Mozambique
Client - Rio Tinto
Contracted to support RIO’s Exploration and Drilling program.
Contract Date – 2011 - 2012
Contract Value – US$ 6.1million
Location - Moatize
Client - Minas Moatize (Beacon Hill Resources)
Principle Mining Contractor
Completion of Overburden Stripping, Bulk Waste and Coal Extraction
Phase 1 - Trial Pit Number 2 (TP2) 1.6 Million BCM’s
Phase 2 - Trial Pit Number 2 (TP2) 1.1 Million BCM’s
Contract Date – March 2009 - 6 months
Contract Value – US$ 820,000
Location - Mozambique
Client - Riverdale Mocambique Limitada
Road Maintenance Project
Completion Date – September 2008 - February 2009
Contract Value – US$ 314,290
Location - Mozambique
Client - Riverdale Mocambique Limitada
Completion Date – 1996
Current Contract Value – US$ 2.9million
Location - Tete, Mozambique
Client: Ministry of Foreign Affairs, Danida Carl Bro International a/s, Denmark Tete
Contract Date: June 2016 - November 2016
Contract Value: US$ 1.3million
Location: Tete, Mozambique
Client: McCormick Property Developments for Largest Shopping Mall in Tete
Contract Date: April 2015 - September 2015
Contract Value: US$ 870,000
Location: Tete
1,400m3 of concrete works for factories and new storage shed.
Contract Date: 10 months
Contract Value: US$ 2.4million
Project: Vale Rail Project
Location: Tete
Contracted to carry out all Major Cut to to Fill Operations of blasted material for the construction of the Vale Rail network linking TETE to the NACALA Port.
Completion Date – Oct 2007 - May 2008
Contract Value – US$ 542,000
Project – Road Re- Habilitation ANE
Location - Linchinga
Client: CMC
Completion Date – 4 months
Contract Value – US$ 789,000
Project – Aveng Pre Cast Factory
Location - Tete
Client: Aveng
Completion Date – 2013
Contract Value – US$ 1.1million
Project – Vale TSF #2
Location - Moatize
Client: Vale Mine
Subcontracted to construct Dam Wall Embankments
190,000 BCM - Load, Haul, Place and Process
Completion Date – November 2012
Contract Value – US$ 480,000
Project – Benga Mine
Location - Moatize, Tete
Client: WBHO
Sub Contracted to WBHO to construct Platforms at Rio Tinto CHPP, to stockpile Thermal coal.
185,000 BCM’s, Load and Haul
Completion Date – February 2010 - April 2010
Contract Value – US$ 400,000
Location: Tete
Client: Riversdale Mocambique Limitada
Trial Pit for Coal Sample Extraction - 225,000 BCM
Completion Date – February 2009 - June 2009
Contract Value – US$ 635,000
Location:
Client: Riversdale Mocambique Limitada
Construction of terraces for a 400 man mine camp
Completion Date – 2006
Contract Value – US$ 281,000
Location - Nampevo
Client: Tamega
Contract Date: Jan 2007 - Aug 2007
Contract Value: US$ 383,000
Project: Rio Ligomha Road
Location: Rio Ligomha
Client: CMC